Those who attended the Brownwood 7-on-7 Division II state qualifier at Gordon Wood Stadium got a first-hand look at the improvements in progress.
Among them, the construction of the new press box – which will not be ready until the 2026 football season – is well underway. Also, the process of the placement of the new bleachers on the home side of the Gordon Wood Stadium has started as well.
At the north end, construction of the new concession stand and restrooms is nearing completion, and a sidewalk and fencing around the north end zone and track are finished.
On the visitors’ side, the press box has received a new paint job, while work continues on the new stairways and switchback ramps, which is an ADA compliance improvement. New bleachers will be installed on that side soon, as well.
All work, with the exception of the new press box, is expected to be complete in time for the Lions’ home opener on Friday, Sept. 5 against Wall.
Renovations are possible due to the passage of a $59,950,000, 20-year bond in May 2023.
A total of $16,300,000 revolves around the following improvements to Gordon Wood Stadium:
- Home bleacher addition (1,000 seats)
- ADA/code improvements (Ramp access, aisles and stairs renovated for code compliance, ADA parking)
- New lights
- New concessions/restrooms
- New press box with elevator
- New turf and track resurface
The lights, turf and track have been completed.